What is the price difference if I buy and have on the job all materials prior to remodeling?

Answered by:

Thomas LeBlanc

A BUILDERS VIEW HOME INSPECTIONS
1 Question Answered
Answered on October 31st, 2018

Hi Steve,I general if you figure  materials  on a new project and double  it that usually  works  out pretty  close,but you can add about 25 percent  more for remodeling.a new home is about  150.00 a square  foot. We usually  work  by the  hour and everyone  is usually  happy. Good  luck,