What time do you start work or have your employees start?

Answered by:

Chris Lougheed

Highly recommended
T&C Contracting group
2 Questions answered
Answered on March 4th, 2018

It depends on the needs of the job. If there is tight deadlines and it’s a requirement to start at 7am. Our guys are in. Generally people that start later work later. Which creates a problem with supervision. As no one is on the job after 430 or 5. So if you have a question and no ones there to answer it you have lost a half day. Sometimes I get my guys to start at noon as there is too many trades onsite to have people work productively. So every job is different. But generally 7am


See all 68 answers